D&C Days QA/QC

One entry point to the whole reconciliation — the field-level matrix, the bore-by-bore listing, the drilling-days resolution, and the revision lineage. Everything below is reachable from this page, and every number traces to committed extractor output.

Reconciled to the article — completion-boundary rule (#846) open
Basis V50 = wed · WAR 2026-02-19
Universe 253 bores · 11 developments
Total 25,404 D&C days
Article 211 bores · 21,944 days
Drilling stability
0/253
bores changed drilling days across vintages
Matrix agreement
7/10
developments tie the article to the day
Open delta
+119days
Jack St Malo — two late bores + #846 boundary
Recovered
25bores
Buckskin, missing from the article's shelf extract

Δ vs the article, by development

Total D&C days, wed minus World Oil Table 1 — seven exact, three explained.

Jack St Malo Buckskin Shenandoah Stones Anchor Cascade Chinook 4 others +119 · open +52 · recovered bore +24 · recompletion 0 · exact 0 · exact 0 · exact 0 · exact 0 +100 days wed − article, total D&C days

The report set

How it holds together

Five report roles, grouped by how deep you're going. Start with the reconciliation narrative, drill into the bore-level data, then follow the one open accounting question. Each card carries an evidence badge so you always know what weight the page can bear.

Guided reading path

If you'd rather be walked through it, follow the reconciliation in the order it was built.

Evidence badges Reconciled / like-for-like Verification / caveat retained Bore-level index Pending / provenance